Today, the battery boxes and superstructure sides were welded. We’re attempting to bend the base plates before we go ahead and begin to weld the drive base. In the meanwhile, here’s some photos of Jesus and his special touch. Jesus welding a battery box The completed welds on the superstructure…
2010 Teams 254/968 Collaborative Build Blog
-
In the hands of Jesus
The events portrayed in this post are from 10:30 PM to 6:47 PM. Events occur in real time. (Que 24 music) 10:30 PM: Kiet and Richard leave West Covina to meet Kirk in Kettleman, CA. 1:40 AM: Goods are exchanged (as pictured) Loading the goods to the Prius All the goods are accounted for […]
2010 Teams 254/968 Collaborative Build Blog
-
Zero to Robot Parts in 6 Hours (or so)
All of the robot chassis and super structure parts were completed today and are on their way to West Covina to be welded and then powercoated. The front plugs will be machined tomorrow and will be mailed down to arrive on Tuesday at the same time that the base plates that Mike D from team 233 made…
2010 Teams 254/968 Collaborative Build Blog
-
Additional Vertical Roller Testing
This was a test using dual 1/2″ rollers wrapped with duct tape. During the test, the rollers separated slightly after coming in contact with the ball once hitting the 3″ limit(simulates a spring loaded roller system). (There was a video here that has sadly been lost in the archives.)
2010 Teams 254/968 Collaborative Build Blog
-
Lifting Arm Calculations
Review the PDF linked below for calculations for the lifting arm. If the PTO is driven on the low gear side (14 to 64), then an additional reduction of approximately 8:1 will be required to drive the arm. This is easily achievable in two stages. If the PTO is driven from the high gear side […]
2010 Teams 254/968 Collaborative Build Blog
-
Vertical Rollers Testing
During the previous two days, we attempted to design and prototype different roller orientations with minimal success. Before we were able to record a video of the horizontal roller setup, we determined that the setup held the ball well(going forward). While attempting to move the prototype…
2010 Teams 254/968 Collaborative Build Blog
-
Today’s Progress
Today we began to manufacture the robot frame. Currently the CNC is turning them out after a laborious 3 passes in order to bore all the holes. Hopefully we will have them done and ready to ship out by tomorrow afternoon. We also furthered our progress on the vacuum prototype, unfortunately with…
2010 Teams 254/968 Collaborative Build Blog
-
Manufacturing and Prototyping Progress
MANUFACTURING Today, construction on the tensioner cams was completed. PROTOTYPING Today we did extensive prototyping with vacuums. We continued to work with the two-stage impeller assembly hooked up to 2 fisher price motors. The impellers are currently running with a 1:1 reduction off of the…
2010 Teams 254/968 Collaborative Build Blog
-
Parts Out for Anodize
We dropped off the wheels, bearing housings, and gearbox spacers at the anodize shop today. Hopefully we should see them back in a few days.
2010 Teams 254/968 Collaborative Build Blog
-
Design, Manufacturing and Prototyping Progress
DESIGN Today, the design team worked to finalize the drivetrain. The baseplate will be sent out to be cut by Mike D at NASA Kennedy’s waterjet shop first thing tomorrow morning. MANUFACTURING The CNC was running all day to cut all of the drivetrain tensioner cams. They will be clear anodized. A…
2010 Teams 254/968 Collaborative Build Blog
-
Manufacturing and Prototyping Progress
Today, Team 254 finished CNCing the wheel hubs for each team and cut the stock needed for the cams. In the meantime, the CAD team continued tweaking the baseplate design and other groups continued working on prototype methods of handling the soccer balls. One of the more successful protoypes the…
2010 Teams 254/968 Collaborative Build Blog
-
Manufacturing Progress
After almost 18 hours of machining the last two days we completed the first operation on all 70 wheels. We began the second operation and now have 20 completed wheels. The rest should be completed in ~3.5 hours tomorrow. We also began making wheel and gearbox spacers.
2010 Teams 254/968 Collaborative Build Blog